Text on page 1
Instruction Manual
PERFECT BINDER
MODEL: DB-280, DB-200, DB-660, DB-700
TEL:886-2-27212117
FAX:886-2-27211669

TEL:886-2-27212117
FAX:886-2-27211669
Page 1 of 69

FIGURE BELOW
MACHINE NOISE
Page 2 of 69

Page 3 of 69

Page 4 of 69

Page 5 of 69

Page 6 of 69

Page 7 of 69

Warning Be careful of the following items that may cause injury or damage.
Application temperature: 260 F (126.67 ℃) to 290F (143.33 ℃)
Working Glue Viscosity: 3,800 to 7,250 CPS
In case of thermostat failure : DB-280 has implemented the secondary thermostat to protect the glue tank temperature over 410F (210。C). When it occurs, the power of DB-280 will be automatically turned off. You have to wait for the glue tank to cool down before you can restart the machine. If this problem occurs again, call your authorized dealer for service.
Page 8 of 69

For your own safety, read the owner's manual carefully. Learn its application and limitations as well as specific potential hazards pertinent to this machine.
For habit of checking to see that keys and adjusting wrenches are remove from the machine before turning it on.
Cluttered areas and benches invite accidents.
Do not use power tools in damp or we locations, or expose them to rain. Keeps work area well illuminated.
All visitors should be kept at a safe distance from work area.
With padlocks, master switches, or by removing starter keys.
It will do the job better and be safer at the rate for which it was designed.
Do not force the machine or attachments to do a job for which they were not designed.
Avoid loose clothing, gloves, neckties, rings, bracelets, or jewelry, which could be caught in moving parts. Nonslip footwear is recommended. Wear protective hair covering to contain long hair.
Use clamps or a vice to hold work when practical. It is safer than using your hand and frees both hands to operate the machine.
Keep proper footing and balance at all times.
Keep machine clean for best and safest performance. Follow instructions for lubricating and changing accessories.
Before servicing and when changing accessories, or when mounting and remounting motor.
Consult the owner's manual for recommended accessories.
Page 9 of 69

If any part is proved to be defective within ONE YEAR from the date of purchase then the manufacturer or distributor shall repair or replace the part provided the defective part is returned immediately to the manufacturer or distributor.
The manufacturer or distributor shall have no obligation to repair or replace those parts failing due to operator carelessness, misuse or due to any cause such as parts failing due to poor lubrication, inadequate cleaning, improper operating environment, improper utilities or operator error.
Page 10 of 69

This machine has warning symbols attached on it as shown below to ensure proper and safe operation.
These symbols are used on the machine to indicate points or instances of specific danger to operating
personnel. Make sure to memorize these symbols and bring them to the attention of others as and when
necessary. Do not remove safety symbols from the machine.
Cutting of fingers or hand rotating blade
Hand Crash/ force from side
Hand Crush/Force from two sides
Cutting of fingers or Hand/moving part
Page 11 of 69

Page 12 of 69

Page 13 of 69

12.6” x 15.75” ( 320mm x 400mm )
3.15” x 1.97” ( 80mm x 50mm )
1.6” ( 40mm )
40 minutes ( varies depending upon glue type )
Glue Warm Up in Stand-by Mode
360 cycles per hour
Up to 200 books per hour
110V, 60 Hz ( Option: 220V, 50 Hz )
49.2”(L) x 22”(W) x 18.5”(H) (1250x560x470mm)
lbs ( 119 Kg )
12.6” x 15.75” ( 320mm x 400mm )
3.15” x 1.97” ( 80mm x 50mm )
1.6” ( 40mm )
25 minutes ( varies depending upon glue type )
Glue Warm Up in Stand-by Mode
360 cycles per hour
Up to 200 books per hour
45.3”(L) x 22”(W) x 14.5”(H) (1150x560x370mm)
lbs ( 116 Kg )
Page 14 of 69

11.7” x 15.53” ( 297mm x 420mm )
5.7” x 5.51” ( 145mm x 140mm )
2.3” ( 60mm )
40~50 minutes ( varies depending upon glue type )
Glue Warm Up in Stand-by Mode
570 cycles per hour
Up to 200 books per hour
110V, 60 Hz ( Option: 220V, 50 Hz )
210~230 Kg ±3 Kg
54.3”(L) x 25.6”(W) x 40.9”(H) (1380x650x1040mm)
11.7” x 8.26” ( 297mm x 210mm )
5.7” x 5.51” ( 145mm x 140mm )
1.57” ( 40mm )
40~50 minutes ( varies depending upon glue type )
Glue Warm Up in Stand-by Mode
620 cycles per hour
Up to 200 books per hour
110V, 60 Hz ( Option: 220V, 50 Hz )
250~270 Kg ±3 Kg
78.7”(L) x 43.3”(W) x 25.6”(H) (2000x1100x650mm)
Page 15 of 69

DECLARED NOISE EMISSION VALUES in accordance with ISO 7960.
Declared A-weighted Sound Power Level, Lward, in dB re 1 pW
Declared A-Weighted Emission Sound Pressure Level , lpAd , in dB re 20 μPa , at the operator’s position.
The values are determined according to specific test code ISO 3746.
The figures quoted are emission levels and are not necessarily safe work levels, whilst there is a correlation between emission and the exposure level. This cannot be used reliably to determine whether or not further precautions are required. Factors that influence the actual level of exposure of work piece include the duration of noise. (i.e. The number of other adjacent machines).
Also, the permissible exposure levels can vary country to country. The information, however, will enable the machine user to make a better evaluation of hazard and the risk.
Page 16 of 69

2.3 Function of the Machine
Page 17 of 69

Page 18 of 69

Page 19 of 69

Page 20 of 69

Page 21 of 69

Page 22 of 69

3.1 Safety Rules for Machine Movement
enough to endure mechanical vibration and to support the weight of the machine for a long time.
ropes, and hooks)As for machine size, make sure the specifications table.
the wire ropes contacts the machine body so that the machine will not get damage.
specifications table about haulage:
Min. room for setting place (L.W.H)
Page 23 of 69

Page 24 of 69

3.3 Selection of Installation Location
Note: You must remove the three red shipping brackets before installing your DB-280
The procedures for installation:
Remove the red shipping bracket located on the left side of the clamp station as shown. Then reinstall the screws in clamp station.
Remove two red shipping brackets that are located around the nipping station as shown.
Please remove the M6 screw which located around the Glue Tank
Lift up your DB-280, slide in the bottom cover first. Then slide in the glue draining tray underneath the glue tank as shown.
Place your DB-280 on a safe, firm and solid table. Then mount the cover-sheet holder to the right side of the machine as shown.
Page 25 of 69

3.5 Installation and Leveling
Tools: adjust screw by screwdrivers ,
The main machine is calibrated by level gauge to hundredth precision
3.6 Power Supply Requirement
Insufficient voltage from factory power source may affect the power output of the motor and the function of the controller.
It is important to connect this machine to the correct voltage in the factory power source. Use only an independent power source.
Table for power supplies requirement:
Page 26 of 69

Check Connection of Power Wires
After the power wires have been connected it is necessary to check if the power wires are connected to the correct connection points.
Check periodically to ensure the following :
The plug is not excessively hot
The power cord is not damaged
The plug is firmly plugged into the outlet
Page 27 of 69

Page 28 of 69

Page 29 of 69

LED Display / Example
Stop all the actions of the machine. Except when “HOT” shows on the LED DISPLAY.
LED
Temporarily lowers the temperature of glue tank so it won’t burn the glue when the machine is not operated.
STBY00
The amount of books bound.
1 ) The amount of books bound.
BIND
ERR = L1
Clear the display counter for books bound.
TAPE
Tape Mode, LCD display “TAPE MODE”
Indicates the “START” button is ready for proceeding to the next operation.
OPEN
LED
Select one of the function modes - MANUAL, AUTO, or PAD.
Select the notching function during the bookbinding operation.
One of the mode indicators will be lit.
When the emergency and Safety function is started, the machine will be stopped immediately and reset all commands, the motor is stopped too. During machining, if any malfunction occurs, press this switch to stop all motion. When restarting machine remember to turn this switch to the right to release it.
Page 30 of 69

(Using the DB-280)
Turn ON the power switch of DB-280 as shown. ( where “I” for ON; “O” for OFF )
The heater of DB‐280 will automatically heat the glue to the preset working temperature
and display the status of the heating processes.The 4 leftmost spaces of LED: the status of
heating process ( COLD, WARM, or HOT ).The 2 rightmost spaces of LED: The elapsed
Start melting the glue. The status is COLD and the elapsed time is one minute for this example as shown.
Melting glue is processing. The status is WARM and the elapsed time is 10 minutes for this example as shown.
After heating for a while, the glue temperature has reached HOT status. The elapsed time is 25 minutes for this example as shown.
When the glue temperature has reached the working temperature, DB-280 performs the self-test and stirs the melting glue.
DB-280 is ready for bookbinding and set to MANUAL mode for your desired operation. At this moment, the control panel will display and flash "LOAD BOOK" for your attention.
For binding operations, please refer to the MANUAL, AUTO and PAD operations.
Page 31 of 69

The glue level may require adjustment when the thickness of the book or pad varies. Use the following book spine illustrations for guidelines.
Too much glue on both sides OR
Adjusting the glue level :
MIN
MAX
MIN
MAX
Page 32 of 69

Note that the thickness of the cover sheet is an important factor for you to make a good spine. Use only the suitable thickness of the cover sheet associated with the appropriate glue-meter position to make a good book.
Page 33 of 69

CAUTION: Great care must be taken when handling hot molten glue. Be sure not to place an excessive amount of glue in the tank at one time. Keep it at such a level that the glue will not go over the redline in the tank while the application drum is rotating. This will prevent glue from spilling out of the tank
Do not attempt to remove the draining tray until the glue cools down.
Note that it’s not necessary to drain the glue frequently if the machine is used constantly under normal working conditions. However, in case the glue has been left unused for a long period of time with the unit in the “ON” position, and the quality is found to be unacceptable, use the glue replacement procedures or call your authorized dealer.
Page 34 of 69

After the “STARTUP” procedures, the DB-280 will automatically set itself MANUAL operation and flashing "LOAD BOOK" display. Note that the “NOTCH” LED is ON.
Note: In case you need to adjust the book block after you have closed the clamps, you can press the "OPEN" button twice to release it. The LED display will show "PUSH CLOSE". After you have adjusted the book block, you have to press "CLOSE" button until the clamps close. Then you will see the flashing "PUSH START" display again.
Page 35 of 69

After the first notching process, the clamp station will remain to the left side of DB-280 and the LED display of the control panel will display and flash "LOAD COVER".
Center the cover sheet and adjust the side guide: Measure the width of the book plus half the thickness of the spine. Then set side guide accordingly.
Place the cover on the nipping station, the “START” LED will be lit and flashing "PUSH START". Then press the “START” button to move the clamp station over the nipping station starting the binding process for the book block and cover sheet.
Note:
If you accidentally remove or drop the cover sheet during the clamping station returning to the nipping station, the control panel will show “COVER?”. At this moment, you have to place the cover on the nipping station and press "START" button to resume the process.
When the display indicates “PUSH OPEN”, press the “OPEN” button to open the clamps. Then, remove the finished book from the right end of the clamp station. Having completed one bound book, the LED display of control panel will count once for the total binding amount as shown. Then the control panel will display and flash "LOAD BOOK" for binding next book.
Repeat step 1 to 5 for more books in “MANUAL” operation.
Page 36 of 69

Note: All books done in this mode must be same thickness.
In the MANUAL mode, make one book. Centering the cover to the centered point and adjust the side guide.
Press “FUNCTION” button to switch to “AUTO” operation. The “AUTO” LED will be lit and display flashing "LOAD
BOOK" as shown. Note:
The “NOTCH” LED is ON. Step 1: Load book to the RIGHT of the red line. Step 2: Slide the book to The far LEFT.
Note: In case you need to adjust the book block after you have closed the clamps, you can press the "OPEN" button twice to release it. The LED display will show "PUSH CLOSE". After you have adjusted the book block, you have to press "CLOSE" button until the clamps close. Then you will see the flashing "PUSH START" display again.
Page 37 of 69

Place the cover sheet onto the nipping station when the display flashing "LOAD COVER". The clamp station will automatically move back to the position above the nipping station and start the binding process for the book block and cover sheet.
Note:
If you accidentally remove or drop the cover sheet during the clamping station return to the nipping station, the control panel will show “COVER?”. At this moment, you have to place the cover on the nipping station and press "START" button to recover the process.
Having completed one bound book, the clamp will automatically open and display "UNLOAD" so that you can remove the finished book from the right end. Meanwhile, the LED display of control panel will count once for the total binding amount as shown. The DB-280 will flash "LOAD BOOK" display.
Place the same thickness of book block onto the clamp as the label instructions on the clamp. The clamp station will automatically clamp down the book block and move to the left. Repeat step 5 to 4 for more books in “AUTO” operation.
Page 38 of 69

“PAD” is one of the DB-280 operations that apply to special binding applications such as binding without cover sheet.
Press “FUNCTION” button to switch to “PAD” operation. The “PAD” LED will be lit and display flashing "LOAD PAD" as shown.
Note: The “NOTCH” LED is normally OFF. But you can press “NOTCH” button to actuate it, if desired.
Step 1: Load book to the RIGHT of the red line. Step 2: Slide the book to The far LEFT.
Note: In case you need to adjust the pad block after you have closed the clamps, you can press the "OPEN" button twice to release it. The LED display will show "PUSH CLOSE". After you have adjusted the pad block, you have to press "CLOSE" button until the clamps close. Then you will see the flashing "PUSH START" display again.
Page 39 of 69

(2) Having moved to the left position of DB-280, the clamp station will automatically move back to the right position and display "WAIT..".
(4) Wait for a few seconds until the LED display of control panel displays “PUSH OPEN” as shown.
Then press the “OPEN” button to open the clamp so that you can withdraw the bound pad block. Meanwhile, the LED display of control panel will count once for the total binding amount. Then the control panel will display and flash "LOAD PAD" for padding next pad.
Note: If glue is too thick on spine, adjust thickness in accordance with
Repeat step 2 to 4 for more books in “PAD” operation.
Page 40 of 69

Press “STANDBY” button, the DB-280 will temporarily lower the temperature of glue tank so it won’t burn the glue when the machine is not operated. The LED displays "STBY00" as shown below. Where "00" is the timer display for the duration of the standby period.
Press “STANDBY” button again when the “STANDBY” LED is on, the DB-280 will reheat the glue tank to the working temperature, then the “READY” LED will be lit and waiting for your desired operation.
Note that you have to wait a few minutes when LED displays "WARM00" status. The glue tank of DB-280 will be reheated, then the control panel will display and flash "LOAD BOOK" after "HOT" status.
Page 41 of 69

INSTALL FOUR OPTIONAL BLOCK PARTS. Press “TAPE” button,LED Display
“TAPE” “MODE"instead of ”LOAD”“BOOK” After clamp station goes to left,LED
display shows ”LOAD” “TAPE” Press “START” after putting tape, book go back right side then finish the tape mode ATTENTION:
It’s same operation in manual or auto mode,please put tape in right postion
TR1 SETTING Press “START” and “TAPE” together,set TR1 only.
This function is available in manual, auto and pad mode. The Nipping timer default 4 sec. TR1 range is 2.0-10sec.
Page 42 of 69

The casing unit is used for adjusting the distance between book sheets and hard cover, adjusting range 0~10mm Tuning angle 0~180degrees
Release the M4 screw first, after
adjusting tight the M4 screw.
When blade cutting,it brings paper dust, so use vacuum dust removal system to clean.
The vacuum pipe size :4”
Page 43 of 69

4.5 Adjustment of the Machine/Components
Function The purpose of notching is to enhance the solidification of the bookbinding. The notching blade makes numerous cuts on the spine of the book so that the melted glue can penetrate the binding area.
In order to get appropriate depth of the cuts and the precision of the center path for clamp station, the notching
station can be adjusted to the up, down, right, and left positions as shown. Note that notching surface should be
adjusted evenly on both sides to prevent tilting the notching surface. Otherwise, the cuts of the book will have one
side deeper than the other. The standard depths of the cuts are 1 mm evenly on the spine of the book.
You also can lift up the notching station to gain the depth of the cuts when the blade has been worn out a little bit. Or you have to change the blade.
Page 44 of 69

Page 45 of 69

Providing a layer of melted glue on the spine of the book so that cover and pages can be bound together . The glue scraper of glue tank controls the quantity of the melted glue on the glue drum while the glue meter controls the thickness of melted glue that is applied to the spine
1.) Set the glue-adjusting knob to the left ( MIN ) position
2.) Use a ruler from the surface of the nipping station across the glue tank as shown on the following page. The ruler should touch the glue meter. Then measure the distance between the ruler and the peak of glue drum. Note that the standard gap between the ruler and the peak of glue drum is 2 to 3 mm.
1.) Loosen the two screws on the glue scraper.
2.) Measure the distance between glue scraper and the glue drum as shown. Note that the standard
gap between glue scraper and the glue drum is 2 mm.
3.) Tighten the screws.
Page 46 of 69

Normally, the indicator is set at 1/3 to 1/2 of the arrow mark.
sheet is an important factor for you to make a good spine. Use only the appropriate thic kness of cover sheet to make a good book.
1.) Decrease the melted glue when:
2.) Increase the melted glue when:
Page 47 of 69

Provided a flat surface for the book block, when there are being placed into the clamp station. It also provides the nipping force to form the cover around the spine of the book
1.) During the nipping process, the nipping plates must exert an even pressure on the cover in order to form a spine
2.) The nipping swing arms provide this pressure
Open the nipping station, then turn the swing arms counter-clockwise to the position shown. The swing arms must touch together at the centerline as shown.
If not, they need to be adjusted.
Page 48 of 69

There are three positions of the nipping station for executing the clamping, the cover, and the nipping processes. The LED of the sensor (LS3 or LS4) goes on when the notch of position disc travels through the trench of the sensor as shown below:
1.) Clamping: when the bearing is at the highest point
2.) Cover: when the bearing is at the lowest point
Page 49 of 69

3.) Nipping: when the bearing is at the sub-high point
If the spine is not being nipped evenly, adjust the nipping plates as follows:
1.) Push each side of nipping plates to find out which side is too tight.
2.) Then use the nipping plate screws to do the fine adjustment until both sides have the same tension.
Note that you can use the“MOTOR2” of “TEST2” to verify the nipping plate position before tightening them.
Nipping plate adjustment screws
Page 50 of 69

TAPE MODE BLOCKS Adjustment / Cover Position Fixed ruler
TAPE mode using tape instead of cover blocks adjusting was as the cover center adjusting. Please install blocks first before your adjustment. Cover position fixed ruler can be pulled out to fix your covers position. Fixed device can fix the ruler firmly in the place you want.
Page 51 of 69

Holding the book block for the notching, gluing, and nipping processes of bookbinding.
The acceptable spine of a book and the shape of book block after being clamped are shown below. If you find different shapes such as “round”, “hollow” and “nail head” for one end or both ends, remove the clamp covers, then adjust the screws on both clamps.
Making book is a top priority (to see where is the machine need to be adjusted ):
The priority way of machine’s measurement is making books. We usually make 5mm, 10mm, 15mm, 20mm as well as 30mmof thickness to inspect. however, 20mm is a standard for us to make sure the spine of the book should be good. Because nail head usually happen in thicker books, and round spine usually happen in thinner books.
2.) How to adjust the angle/pressure of the clamp plate If you need to adjust the clamp plate, please refer to following points:
Page 52 of 69

LL and LR corners are nail head: it means that the left spine of the book should be lift up to make the left side of the spine rounder. So you can increase adjustment on both NON-OP Plate1 and OP Plate 1,and
making book to see LL and LR corners are ok or not.
LL corner is nail head: it means that the LL corner should be lift up to make the LL corner rounder, So you can increase adjustment on NON-OP Plate 1,, and then making book to see LL corner is ok or not.
LR corner is nail head: it means that the LR corner should be lift up to make the LR corner rounder, So you can increase adjustment on OP Plate 1, making book to see LR corner is ok or not.
RL and RR corners are nail head: it means that the right spine of the book should be lift up to make the right side of the spine rounder. So you can increase adjustment on both NON-OP Plate 3 and OP Plate 3,,
and then making book to see RL and RR corners are ok or not.
RL corner is nail head: it means that the RL corner should be lift up to make the RL corner rounder, So you can increase adjustment on NON-OP Plate 3, and then making book to see RL corner is ok or not.
RR corner is nail head: it means that the RR corner should be lift up to make the RR corner rounder, So you can increase adjustment on OP Plate 3, and then making book to see RR corner is ok or not.
All above are nail head situation, if round spine or corner happened, please refer to following point:
Page 53 of 69

LL and LR corners are round: it means that the left spine of the book should be push down to make the left side of the spine to be more right angle. So you can increase adjustment on both NON-OP Plate 2 and OP Plate 2, and then making book to see LL and LR corners are ok or not.
LL corner is round: it means that the LL corner should be push down to make the LL corner to be more right angle, So you can increase adjustment on NON-OP Plate 2,and then making book to see LL corner is
LR corner is round: it means that the LR corner should be push down to make the LR corner to be more right angle, So you can increase adjustment on OP Plate 2, and then making book to see LR corner is ok or
RL and RR corners are round: please refer to above steps to work on NON-OP Plate 4 and OP Plate 4. RL corner is round: please refer to above steps to work on NON-OP Plate 4. RR corner is round: please refer to above steps to work on OP Plate 4.
Page 54 of 69

Provides driving power to move and locate the clamp station over the glue drum and notching station, then return it back to the nipping station for covering and binding.
Adjust tensioner to eliminate any slack in chain
5.1 Day/Month/Year Maintenance Daily Cleaning Procedures
After you have finished using the binder for the day, follow the following steps:
1.Close the clamps while the LED display flashing "LOAD BOOK" or "LOAD PAD". 2.Press "START" and "CLEAR" keys simultaneously. The clamp station will automatically move to the left of the machine and LED display "NP SVC".
Depends on how frequency you use the machine, we recommend that you should do the following maintenance at least once during three-month period.
Page 55 of 69

1. Open the clamps to the maximum position then turn off the power of the machine.
2. Take apart the clamps from the clamp station.
3. Clean the residual glue that might be on the clamps.
4. Install the clamps to the clamp station.
5. Turn on the power of the machine.
6. Clamp some inner pages to see if the clamps have been installed properly. If clamp adjustment need, please refer to A1 section of Appendix for details.
(2) Notching Station This is a monthly maintenance. However, we recommend that you should use vacuum to clean the paper dust on the notching station when the machine has made 2,000 books.
Warning: You must power off the machine in order to perform the notching blade maintenance.
5.1.1 All operating components such as chains, chain sprockets, gears, racks shall be routinely added with lubricating oil or grease. 5.2.2 All rotating joints at spindle ends attached with oil cups shall be routinely filled with lube oil.
In case, when the control panel display error message, please refer to following step to correct.
Page 56 of 69

Page 57 of 69

Page 58 of 69

Page 59 of 69

5.4 Test Of Safety Devices
Press and hold down the “FUNCTION” and “START” buttons, then turn the power on. You should see the “TEST1” in the LED display. After performing the “WARM”, “HOT”, and “S-TEST” processes, the DB-280 will execute the entire operation test procedures as the following order:
Open the clamps ¢ Close the clamps ¢ Move clamp station to pass the notching station / Run the notching wheel
¢ Back to nipping station ¢ Up/Down the nipping station / Close/Open the nipping plates
Note: Test1 is an infinite loop. To return to MANUAL operation, you can stop Test1 by pressing the FUNCTION button when the LED display shows "READY".
Press and hold down the “FUNCTION” and “STANDBY” buttons, then turn the power on. You should see the “TEST2” in the LED display. After performing the “WARM”, “HOT”, and “S-TEST” processes, the DB-280 will display “MOTOR 1” in the LED display. Then you can select the following module tests by pressing “OPEN” or “CLOSE” button to toggle “MOTOR 1”, “MOTOR 2”, “MOTOR 4”, and “MOTOR 6” followed by pressing “START” button to execute.
MOTOR 1 (Main motor motion): Moves clamp station to notching station, then back to nipping station.
MOTOR 2 (Nipping motor motion): Moves the nipping station surface to the highest point, the sub-high point, and the lowest point and provides the nipping force for nipping plates.
MOTOR 4 (Notching motor motion):
Runs the notching wheel for a few seconds.
MOTOR 6 (Clamp motor motion)
Opens the clamps, then close the clamps.
Note: To return to MANUAL operation, press FUNCTION button when LED display shows "MOTOR1/2/4/6".
Press and hold down the “FUNCTION” and “CLEAR” buttons, then turn the power on. You should see the total amount of bookbinding in the LED display.
Page 60 of 69

6.1 Safety Rules For Electrical Control System
1.) Only personnel who are properly trained and have adequate knowledge and skill should undertake all electrical/electronic troubleshooting and repair.
2.) Do not alter or bypass protective interlocks.
3.) Before starting, read and observe all warning labels.
4.) When trouble shooting make sure the power source has been disconnected and main switch has been locked.
5.) Take extra precautions in damp areas to protect you from accidental grounding.
6.) Before applying power to any equipment it must be established, without a doubt, that all persons are clear.
7.) Do not open the electrical control panel unless it is necessary to check the electrical equipment.
8.) Do not alter the electrical circuits unless authorized to do so by the manufacturer.
9.) When replacing electrical components, make sure they conform to the manufacturer's specifications, including proper colour coding.
10.) Do not wear metal frame glasses, metallic necklaces or chains while working on any electrical equipment. Also do not wear any ring, watch or bracelet while operating electrical equipment.
Page 61 of 69

Page 62 of 69

Page 63 of 69

Page 64 of 69

Page 65 of 69

Page 66 of 69

Page 67 of 69

Page 68 of 69

4RK25GN
5TK50GN
5IK40A
2GN30K
Z-15GW-B
Page 69 of 69 ยท End of manual
| Problem | Likely cause | Fix (from the manual) |
|---|---|---|
| Machine shuts off by itself | Secondary thermostat tripped because the glue tank went over 410 degF (210 degC) | Wait for the glue tank to cool before restarting. If it happens again, call your authorized dealer for service. Page 8 |
| Display shows "COVER?" | Cover sheet removed or dropped while the clamp station returned to the nipping station | Place the cover on the nipping station and press START to resume. Page 36 |
| Too much or too little glue on the spine | Glue level not matched to book or pad thickness | Loosen the glue adjustment lock knob, slide it right for more glue or left for less, then turn it clockwise to lock. Page 32 |
| Poor glue quality | Glue left unused for a long time with the unit ON | Drain and replace the glue using the glue replacement procedure, or call your authorized dealer. Page 34 |
Use only the suggested hot melt glues with an application temperature of 260°F to 290°F and a working viscosity of 3,800 to 7,250 CPS. See page 8.
Press FUNCTION to select MANUAL, AUTO or PAD. AUTO is for books of the same thickness, so make one book in MANUAL first to center the cover and set the side guide. See page 37.
Measure the width of the book plus half the spine thickness and set the side guide to that. See page 36.
Warm up the machine, put the foil-lined draining tray under the tank, loosen the drain Allen screw with a 6 mm Allen wrench, close it when the glue stops flowing, then add new glue below the red line. See page 34.
Close the clamps, press START and CLEAR together to move the clamp station left ("NP SVC"), clean glue from the nipping plates, press START and CLEAR again, open the clamps fully, clean and wax them, and turn the binder off. See page 55.